Breakthroughs in transport infrastructure development

In 2015, Deo Ca Investment JSC-investor of Ca Pass tunnel Project -has allowed traffic through Co Ma tunneland organized the groundbreaking ceremony for Cu Mong tunnel construction. Ca Pass tunnel construction progress is also being accelerated, ensuring traffic engineering in 2016 and being completed in 2017. Meanwhile, the project of upgrading and expanding Highway 1 through Phu Yen has allowed traffic, facilitating smooth transporation for people.

Workers passionately working in Ca Pass tunnel

Workers passionately working in Ca Pass tunnel

During the last days of the lunar year, the working atmosphere at construction sites of Ca Pass tunnel is more dynamic and urgently. Although Tet is imminent, nearly 700 officers and workers, foreign experts are still working here withengrossed spirit. At Co Ma tunnel,after technical traffic ceremony on September 26th, 2015, contractors performing this category-Song Da 10 Joint Stock Company-conducted the installation of lighting equipment, ventilation and drainage systems … for early complete coverage. The space inside the 500m long tunnel tubes is full of electric light, people are urgently racing against time.

Captain Vu Tien Trung, the Commander of the east tunnel (the underground Construction Company-Lung Lo Construction Head Company), said: Currently, each day, the unit can drill 5-6m oftunnel belonging to geological of construction. Although working in extreme conditions while deep inside the mountain, all the officers and soldiers of Lung Lo Construction Head Company got some time, working day and night. In the last Lunar New Year, because of the work schedule requirements, the unit had to welcome Tet and work at the working site. And this Lunar new year, workers will return to work soon after the New Year holiday with greater determination to accelerate the pace of drilling tunnels.

Mr. Le Quynh Mai, Deputy General Director of Deo Ca Investment JSC, said: Until now, contractors have drilled more than 3,200 out of 4,125m tunnel. As scheduled for May 2016, Deo Ca tunnel will be open to traffic engineering. The contractors are also focused on completing the lane, bridge on the route and other items so as to put Ca Pass and Co Ma Pass tunnels into operation in 2017. For Cu Mong tunnel, Deo Ca Investment JSC will try to finish a basement garage so that vehicles can flow in the shortest time.

Being started in the end of 2013, after nearly two years of urgent implementation, the project of upgrading and expanding Highway 1 running through Phu Yen has been open to traffic engineering. This is the national key projects, with the total length of more than 63,5km, the total investment of 4,350 billion dongs. Traveling on Highway 1 upgraded in new condition, people are very excited. Ms. Tran Thi Loan in Dong Hoa district, shared: Since Highway 1 was upgraded, the slope at this location has been reduced, the road is flat, with median and frontage roads at both ends of the horizontal line so the travel is much more convenient. As for Mrs. Pham Thi Hanh, an elderly in Tuy An district, since the rail overpass was built, medium pressure at Chi Thanh barrier has decreased, the appearance of the townlet has also become more modern. This is the dream of the people for many years.

Source: Phu Yen NewspaperTranslated by TRONG HAO